Net zero risk register

Show all parts of this guide

7. Services and budgets at risk from climate related failure and global effects on the energy system

Risk Title and Description

Services and budgets at risk from climate related failure and global effects on the energy system.

Service: Net Zero & Business

Date identified: 6 February 2023

Owner: Net Zero Project Manager

Target implementation date: 2030

Potential Causes:

  • Power outages as result of wind, heat, ice and snow
  • Impact of war affecting national energy supply, security and economic toll

Potential Impacts:

  • Essential services not being carried out
  • High expenditure/ budget overspend/ affordability
  • Increase in the cost to run the service affected

 

Existing Mitigations & Control

What has been done to control the risk?

  • Installation of solar PV across corporate estate and Council housing to reduce reliance on national grid
  • Installation of battery storage technology at Water Lane, Matford Centre, John Lewis Car Park and Riverside allowing for smart grid use

 

Further Mitigations & Controls to be put into place

  • Continue to investigate renewable energy opportunities to identify and fund solar PV and other renewable energy supply opportunities for the corporate estate and housing

 

Notes

Funding required is limited by scope of grants, and current financial instability including cost of borrowing.

 

Risk scores

Inherent risk
Risk Score
Likelihood 3
Impact 2
Risk score 6

 

Residual risk
Risk Score
Likelihood 2
Impact 2
Risk score 4

 

Risk scores explained